    Red face Siding a dormer

    On a gable style dormer on a sloped roof, must the vinyl siding on the side of the dormer be an inch or two above the shingles, overlapping the flashing? Thanks guys.

    Similar Threads:
    Inspection Referral

  2. #2
    Join Date
    Mar 2007
    Location
    Connecticut
    Posts
    1,828

    Default Re: Siding a dormer

    Not so important with vinyl as there is no decay aspect from water wicking up into shingle ends, but if it is the first layer of roofing there will be no room for another layer making reroofing more expensive for no good reason. 3/4 gap would allow second layer install with no problem.
    If it is the second layer it is fine as the roof will have to be stripped next time anyway.


  3. #3
    Join Date
    Mar 2008
    Location
    southern ontario
    Posts
    130

    Default Re: Siding a dormer

    Yes that was my thinking, there wouldn't be a wicking problem but good advice about the possibility of adding another layer of shingles. Thanks Wayne


  4. #4
    Join Date
    Mar 2007
    Location
    Fletcher, NC
    Posts
    28,042

    Default Re: Siding a dormer

    Brian,

    You are close to being correct, you have the right idea, just the wrong clearance.

    The specified clearance between roof shingles and the 'J' channel is 1/2" MINIMUM, so, yes, 1" or so would be good as well.

    Go here ( http://www.vinylsiding.org/publicati...2007Manual.pdf ), go to page 22, Figure 34.

    Jerry Peck
    Construction/Litigation/Code Consultant - Retired
    www.AskCodeMan.com

  5. #5
    Join Date
    Mar 2008
    Location
    southern ontario
    Posts
    130

    Default Re: Siding a dormer

    Thanks Jerry and thanks for the thread!


  6. #6
    Join Date
    Mar 2007
    Location
    Plano, Texas
    Posts
    4,245

    Default Re: Siding a dormer

    http://www.vinylsiding.org/publicati...2007Manual.pdf
    Check out this generic installation manual or see your brand of siding specific instructions. There is a diagram on page 27 and the full text which includes the excerpts below.



    Keep the J-channel a minimum of 1/2” (12.7mm) from the roof line. Chalk a straight line up

    the roof fl ashing to guide J-channel installation. Tip: You can use another J-channel laid over
    the shingles as a spacer to create the straight line desired.

    NOTE: Vinyl J-channels should not be in
    direct contact with roofing shingles, since
    the shingles may transfer enough heat to
    the vinyl J-channel to cause its distortion.




    Jim Luttrall
    www.MrInspector.net
    Plano, Texas

  7. #7
    Join Date
    Mar 2007
    Location
    Plano, Texas
    Posts
    4,245

    Default Re: Siding a dormer

    You typed faster Jerry!

    Jim Luttrall
    www.MrInspector.net
    Plano, Texas

  8. #8
    Join Date
    Mar 2007
    Location
    Chicago, IL
    Posts
    2,797

    Default Re: Siding a dormer

    For reports...

    ***IMPORTANT*** You Need To Register To View Images ***IMPORTANT*** You Need To Register To View Images
    Michael Thomas
    Paragon Property Services Inc., Chicago IL
    http://paragoninspects.com

  9. #9
    Ted Menelly's Avatar
    Ted Menelly Guest

    Default Re: Siding a dormer

    My last concern would be for a second layer of shingles as I have never recommended more than one layer. There is no money savings. A second layer loses years off its life so won't last as long. Later removing two layers is much more expensive to remove and haul away. Possibility of leaks is much greater.

    Just some thoughts


  10. #10
    Join Date
    Mar 2008
    Location
    southern ontario
    Posts
    130

    Default Re: Siding a dormer

    Thanks men!! Appreciated.


  11. #11
    Join Date
    Mar 2007
    Location
    Fuquay Varina, NC
    Posts
    1,074

    Default Re: Siding a dormer

    The "j" in contact with the roof does turn brown and distort. I have seen it many times. Most builders now hold it up you still find some that don't.

    Besides what has been mentioned is nailing the channel through the step flashing so close to the roof. I have in the past repaired many holes from channels causing leakage. Worst place is at a valley pan against a wall. You spend all this time putting in this nice pan folded up the wall 7" AND THEY NAIL THERE CORNER POST & CHANNEL RIGHT AT THE BOTTOM. I got most builders to get there subs to hold 4" up at the pan then taper back down to the 1" requirement on the siding. The corner post would be notched on the side that can't be seen anyway. Water then can flow freely with out building up debris.

    Mike Schulz License 393
    Affordable Home Inspections
    www.houseinspections.com

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •