You are currently viewing InspectionNews as a guest which gives you limited access to view most discussions but not pictures. There are over 6,300 inspectors who have already joined. By joining InspectionNews you will be able to see the pictures, have access to post topics, communicate privately with other members, respond to polls, upload content and access many other special features. Registration is fast and simple so please, join InspectionNews today!

If you have any problems with the registration process or your account login, please contact us.

Why join InspectionNews? Read the Testimonials
Reply
 
LinkBack Thread Tools Search this Thread
  #1 (permalink)  
Old 09-29-2007, 01:15 PM
Aaron Miller Aaron Miller is offline
Senior Member
 
Join Date: Mar 2007
Location: Nowhere, USA
Posts: 828
Slab-on-Grade Engineering Required?
After years of reading the IRC deferring to the IBC deferring to PTI and looping around endlessly, interrupted only here and there by exceptions allowing the building official to decide this and that, I still cannot make an air-tight argument that a slab-on-grade in expansive soil must be:

(1) designed by an engineer or "design professional"

(2) inspected by that engineer during the process

While I'm at it, how about soil testing to proceed the construction of the above foundation? PTI says that soil testing "shall" occur. IRC and IBC say that you must adhere to PTI requirements, but then say the building official can decide.

Jeez! Any ideas here?

Thanks,

Aaron
Reply With Quote
  #2 (permalink)  
Old 09-29-2007, 02:34 PM
Bruce Breedlove's Avatar
Bruce Breedlove Bruce Breedlove is offline
Member
 
Join Date: Mar 2007
Location: Colorado Springs, CO
Posts: 677
Re: Slab-on-Grade Engineering Required?
Part of a soils test is to determine the bearing capacity of the soil. The engineer must know the soil bearing capacity in order to design the footings.
__________________
"Baseball is like church. Many attend but few understand." Leo Durocher
Bruce Breedlove
www.avaloninspection.com
Reply With Quote
  #3 (permalink)  
Old 09-29-2007, 03:11 PM
Richard Rushing's Avatar
Richard Rushing Richard Rushing is offline
Member
 
Join Date: Mar 2007
Location: Duncanville, Tx
Posts: 1,086
Re: Slab-on-Grade Engineering Required?
Quote:
Originally Posted by Aaron Miller View Post
After years of reading the IRC deferring to the IBC deferring to PTI and looping around endlessly, interrupted only here and there by exceptions allowing the building official to decide this and that, I still cannot make an air-tight argument that a slab-on-grade in expansive soil must be:

(1) designed by an engineer or "design professional"

(2) inspected by that engineer during the process

While I'm at it, how about soil testing to proceed the construction of the above foundation? PTI says that soil testing "shall" occur. IRC and IBC say that you must adhere to PTI requirements, but then say the building official can decide.

Jeez! Any ideas here?

Thanks,

Aaron

Aaron, I always have read into the IRC the same as you (follow the Post Tension Institute recommendations).

Where the PTI states 'SHALL', I take this to mean that THERE IS NO OPTION-- shall means you 'will' to it this way.

So, when the IRC refers to the PTI (that says that soil testing *shall* occur), that means that the IRC is defering the to tighter/ higher demand.
__________________
"If con is the opposite of pro, is Congress the opposite of progress?"
Richard Rushing, HCRI
Duncanville, Tx.
Reply With Quote
  #4 (permalink)  
Old 09-29-2007, 08:50 PM
Jerry Peck Jerry Peck is offline
Member
 
Join Date: Mar 2007
Location: Ormond Beach, Florida
Posts: 7,728
Re: Slab-on-Grade Engineering Required?
One is not allowed to do a post tension slab *without* engineering. Period.

But was that the question you were asking?

I think this answers the question *I* thought you were asking.

From the IRC (underlining and bold are mine)
- R401.4.2 Compressible or shifting soil. Instead of a complete geotechnical evaluation, when top or subsoils are compressible or shifting, they shall be removed to a depth and width sufficient to assure stable moisture content in each active zone and shall not be used as fill or stabilized within each active zone by chemical, dewatering or presaturation.

In other words, one *can* have the geotechnical testing and following engineering done to design a slab sufficient to withstand movement caused by the soil, but, *IF* one *is not* going to do any soil testing and engineering, one SHALL remove that soil to a depth and width sufficient to assure ... blah-blah-blah.
__________________
Jerry Peck, Construction / Litigation Consultant
Construction Litigation Consultants, LLC ( www.ConstructionLitigationConsultants.com )
Reply With Quote
  #5 (permalink)  
Old 09-30-2007, 10:51 AM
Aaron Miller Aaron Miller is offline
Senior Member
 
Join Date: Mar 2007
Location: Nowhere, USA
Posts: 828
Re: Slab-on-Grade Engineering Required?
Quote:
Originally Posted by Jerry Peck View Post
One is not allowed to do a post tension slab *without* engineering. Period.

But was that the question you were asking?

I think this answers the question *I* thought you were asking.

From the IRC (underlining and bold are mine)
- R401.4.2 Compressible or shifting soil. Instead of a complete geotechnical evaluation, when top or subsoils are compressible or shifting, they shall be removed to a depth and width sufficient to assure stable moisture content in each active zone and shall not be used as fill or stabilized within each active zone by chemical, dewatering or presaturation.

In other words, one *can* have the geotechnical testing and following engineering done to design a slab sufficient to withstand movement caused by the soil, but, *IF* one *is not* going to do any soil testing and engineering, one SHALL remove that soil to a depth and width sufficient to assure ... blah-blah-blah.
JP:

Good point.

Thanks,

Aaron
Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Slab-on-Grade Aaron Miller Sub-Structure: Home Inspection and Commercial Inspection 11 09-28-2007 05:35 PM
Slab question Paul Tooley Structural Components: Home Inspection and Commercial Inspection 4 07-24-2007 08:27 PM
Floor Covering Required? Joe Nernberg Building Interior: Home Inspection and Commercial Inspection 16 06-15-2007 01:16 AM
Sweeping Required? Dale W. Feb Fireplaces, Chimneys and Solid Fuel Burning Appliances: Home Inspection and Commercial Inspection 12 06-12-2007 05:01 PM
Vapor barrier not required w/ Hardi Plank? Eric Laney Building Envelope: Home Inspection and Commercial Inspection 20 05-01-2007 11:55 AM


All times are GMT -7. The time now is 11:22 PM.


Design by Vjacheslav Trushkin.
Powered by vBulletin® Version 3.6.5
Copyright ©2000 - 2008, Jelsoft Enterprises Ltd.
Search Engine Optimization by vBSEO 3.0.0 RC8
vB.Sponsors
All Rights Reserved. Hann Tech Marketing Link / InspectionNews.com / InspectionNews.net - No part of InspectionNews.net may be reproduced in any way, or by any means, without the prior written permission of InspectionNews.net. Use of any index or listing Software for the purpose of constructing a mailing list, creating promotional materials or producing a printed or electronic catalog of any kind is expressly forbidden without the prior written permission of InspectionNews.net - All text, graphics and design on InspectionNews.net is copyright by Hann Tech Marketing Links.
Ad Management by RedTyger