Registration is FREE!... and will get rid of this top message
Welcome to InspectionNews.net.
You are currently viewing InspectionNews as a guest which gives you limited access to view some discussions but none of the pictures.
There are over 9,970 inspectors who have already joined. By joining InspectionNews you will be able to see the pictures, post new topics or reply to others, communicate privately with other members, respond to polls, upload content and access many other special features.
Registration is FREE for you because the sponsors pay your way. Please visit the sponsors often and let them know that you found them on InspectionNews!
Registration is FREE, fast and easy so please, join InspectionNews today!
Why join InspectionNews? Read the Testimonials
Looking for Education? We recommend Casey, O'Malley and Associates

If you have any problems with the registration process or your account login, please contact us.
|
|

09-29-2007, 01:15 PM
|
|
|
|
Slab-on-Grade Engineering Required?
After years of reading the IRC deferring to the IBC deferring to PTI and looping around endlessly, interrupted only here and there by exceptions allowing the building official to decide this and that, I still cannot make an air-tight argument that a slab-on-grade in expansive soil must be:
(1) designed by an engineer or "design professional"
(2) inspected by that engineer during the process
While I'm at it, how about soil testing to proceed the construction of the above foundation? PTI says that soil testing "shall" occur. IRC and IBC say that you must adhere to PTI requirements, but then say the building official can decide.
Jeez! Any ideas here?
Thanks,
Aaron 
|
|

09-29-2007, 02:34 PM
|
 |
Member
|
|
Join Date: Mar 2007
Location: Colorado Springs, CO
Posts: 811
|
|
|
Re: Slab-on-Grade Engineering Required?
Part of a soils test is to determine the bearing capacity of the soil. The engineer must know the soil bearing capacity in order to design the footings.
__________________
"Baseball is like church. Many attend but few understand." Leo Durocher
Bruce Breedlove
www.avaloninspection.com
|
|

09-29-2007, 03:11 PM
|
 |
Member
|
|
Join Date: Mar 2007
Location: Duncanville, Tx
Posts: 1,097
|
|
|
Re: Slab-on-Grade Engineering Required?
Originally Posted by Aaron Miller
After years of reading the IRC deferring to the IBC deferring to PTI and looping around endlessly, interrupted only here and there by exceptions allowing the building official to decide this and that, I still cannot make an air-tight argument that a slab-on-grade in expansive soil must be:
(1) designed by an engineer or "design professional"
(2) inspected by that engineer during the process
While I'm at it, how about soil testing to proceed the construction of the above foundation? PTI says that soil testing "shall" occur. IRC and IBC say that you must adhere to PTI requirements, but then say the building official can decide.
Jeez! Any ideas here?
Thanks,
Aaron 
Aaron, I always have read into the IRC the same as you (follow the Post Tension Institute recommendations).
Where the PTI states 'SHALL', I take this to mean that THERE IS NO OPTION-- shall means you 'will' to it this way.
So, when the IRC refers to the PTI (that says that soil testing *shall* occur), that means that the IRC is defering the to tighter/ higher demand.
__________________
"If con is the opposite of pro, is Congress the opposite of progress?"
Richard Rushing, HCRI
Duncanville, Tx.
|
|

09-29-2007, 08:50 PM
|
 |
Member
|
|
Join Date: Mar 2007
Location: Ormond Beach, Florida
Posts: 14,293
|
|
|
Re: Slab-on-Grade Engineering Required?
One is not allowed to do a post tension slab *without* engineering. Period.
But was that the question you were asking?
I think this answers the question *I* thought you were asking.
From the IRC (underlining and bold are mine)
- R401.4.2 Compressible or shifting soil. Instead of a complete geotechnical evaluation, when top or subsoils are compressible or shifting, they shall be removed to a depth and width sufficient to assure stable moisture content in each active zone and shall not be used as fill or stabilized within each active zone by chemical, dewatering or presaturation.
In other words, one *can* have the geotechnical testing and following engineering done to design a slab sufficient to withstand movement caused by the soil, but, *IF* one *is not* going to do any soil testing and engineering, one SHALL remove that soil to a depth and width sufficient to assure ... blah-blah-blah.
|
|

09-30-2007, 10:51 AM
|
|
|
|
Re: Slab-on-Grade Engineering Required?
Originally Posted by Jerry Peck
One is not allowed to do a post tension slab *without* engineering. Period.
But was that the question you were asking?
I think this answers the question *I* thought you were asking.
From the IRC (underlining and bold are mine)
- R401.4.2 Compressible or shifting soil. Instead of a complete geotechnical evaluation, when top or subsoils are compressible or shifting, they shall be removed to a depth and width sufficient to assure stable moisture content in each active zone and shall not be used as fill or stabilized within each active zone by chemical, dewatering or presaturation.
In other words, one *can* have the geotechnical testing and following engineering done to design a slab sufficient to withstand movement caused by the soil, but, *IF* one *is not* going to do any soil testing and engineering, one SHALL remove that soil to a depth and width sufficient to assure ... blah-blah-blah.
JP:
Good point.
Thanks,
Aaron 
|
|
| Thread Tools |
Search this Thread |
|
|
|
Posting Rules
|
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts
HTML code is Off
|
|
|
| Thread |
Thread Starter |
Forum |
Replies |
Last Post |
| Slab-on-Grade |
Aaron Miller |
Sub-Structure: Home Inspection and Commercial Inspection |
11 |
09-28-2007 05:35 PM |
| Slab question |
Paul Tooley |
Structural Components: Home Inspection and Commercial Inspection |
4 |
07-24-2007 08:27 PM |
| Floor Covering Required? |
Joe Nernberg |
Building Interior: Home Inspection and Commercial Inspection |
16 |
06-15-2007 01:16 AM |
| Sweeping Required? |
Dale W. Feb |
Fireplaces, Chimneys and Solid Fuel Burning Appliances: Home Inspection and Commercial Inspection |
12 |
06-12-2007 05:01 PM |
| Vapor barrier not required w/ Hardi Plank? |
Eric Laney |
Building Envelope: Home Inspection and Commercial Inspection |
20 |
05-01-2007 11:55 AM |
All times are GMT -7. The time now is 09:50 PM.
| | |
|